Status |
Standing |
Type |
Chairlift - Double - Fixed |
Brand |
Borvig |
Install Season |
2018-19 |
New Install? |
|
Ancestors |
Betwixed Double, Stratton, VT
|
Cost |
|
Install Length |
|
Install Vertical |
|
Final Season Standing |
|
Descendants |
| Notes |
Construction started on this lift, likely the former Stratton Betwixed Double, in 2003, following the Sun Corner Triple lift line. Initial work included concrete footings and some towers. Incremental construction took place in subsequent years, including work on the base and summit terminals.
Construction resumed in 2017. Lift opened 1/5/19. |
|
|