Avalanche Double
Mt. Southington Connecticut
|
Status |
Standing |
Type |
Chairlift - Double - Fixed |
Brand |
Partek |
Install Season |
2021-22 |
New Install? |
|
Ancestors |
Avalanche Double, Mt. Southington, CT
|
Cost |
|
Install Length |
2,069 feet |
Install Vertical |
357 feet |
Final Season Standing |
|
Descendants |
| Notes |
Avalanche Hall-Partek double rebuilt with Partek towers, chairs, and top terminal in 2021. |
|
|
 The base terminal (December 2021)
 Footing construction (October 2021)
 Footing construction (October 2021)
 Footing construction (October 2021)
 Footing construction (October 2021)
 Footing construction (October 2021)
 New towers (November 2021)
 The top terminal (December 2021)
 The lift line (January 2022)
 The lift line (February 2022)
 The lift line (February 2022)
|
|